The PUSD Witter Field Renovation Project Update 7-13-23 provides an update from Pete Palmer, PUSD Director of Facilities/Construction Manager, on anticipated parking restrictions and other impacts for the remainder of July, as well as an update on the drainage calculations.
Look Ahead Schedule Highlights - see full schedule here.
7/10/23-7/14/23 Grading at Field and Off-Haul
7/17/23-7/28/23 Storm Drainage
7/12/23-7/26/23 Grade at Upper Bleachers
7/25/23-7/28/23 Electrical at Upper Bleachers
7/24/23-7/28/23 Channel Drains
7/31/23-8/11/23 Concrete at Bleachers